12 months behind schedule and still no satisfactory explanation for the delay
No news on opening date for the Poppleton Bar “hyper hub” or recharging costs
The Councils media release reads:
- Monks Cross HyperHub is one of the largest charging hubs in Northern England
- Four 175kW ultra-rapid chargers, four 50kW rapid chargers, with an adjacent area having 30 7kW chargepoints
- Solar canopy allows site to generate renewable energy which can be stored in batteries at both Monks Cross and Poppleton

York’s new electric vehicle HyperHub at Monks Cross is open from today [15 June]. For a limited time, the new site won’t be charging for electricity in a bid to test the new technology and encourage residents and visitors to visit the new site.
The Monks Cross HyperHub is located next to Park and Ride site and will be one of the largest charging hubs in Northern England. Poppleton HyperHub is set to open this summer.
Both HyperHub sites will contain 4 Ultra-Rapid (150kW) and 4 Rapid (50kW) vehicle chargers, helping to support the uptake of modern EV’s that have larger battery capacities and are capable of Ultra Rapid charging.
Monks Cross features four 175kW ultra-rapid chargers (which can be upgraded to 350kW when vehicle charging rates make that worthwhile), four 50kW rapid chargers, with an adjacent area having thirty 7kW chargers for Park and Ride users.
The HyperHub also has a solar canopy which allows the site to generate its own renewable energy which can be stored in the Tesla Powerpack batteries at the charging hub, helping to reinforce the grid.
The ultra-rapid and rapid chargers are user-friendly for EV drivers and offer contactless payment methods. Cars and vans can access the chargers, and the facility has been designed with no kerbs to allow disabled access. Protection from the weather is provided by the solar canopy and all of the electricity supplied from the National Grid will be generated by renewable sources.
A key element behind the development of the HyperHubs was the production of an Electric Vehicle Charging Strategy by the council. This looked at a wide range of issues in order to ensure that the HyperHubs met the needs of residents, fleets, commuters and through traffic. The convenient location of the charging hubs was a central part of the strategy, with the first two HyperHub sites being located off the ring road next to established Park and Ride sites.
The Electric Vehicle Charging Strategy also identified that it wasn’t yet commercially viable for the private sector to develop such charging hubs, so the council would own its charging network in order to guarantee the best results for residents. This allows the council to plan how the network will grow and to set tariffs, as well as making it directly accountable and enabling it to deliver next generation chargers as quickly as possible.
The funding for the HyperHubs is also unique, with City of York Council successfully securing £1 million of European Regional Development Funding and £800,000 from the Office for Zero Emission Vehicles, along with £400,000 of the council’s own capital funding to install the first two HyperHubs. This has resulted in 80% of the £2.2 million project being externally funded.
For more information about the HyperHubs visit https://www.york.gov.uk/hyperhubs
There was a slight delay to the originally planned completion date of Monks Cross due to finalising commercial and contractual arrangements. There is no additional cost as a result of this delay. (!)
The unique project is the result of a partnership between City of York Council and EvoEnergy.